About the Project

As part of an ongoing commitment to enhancing wireless service, T-Mobile and AT&T have identified your community as a key area in need of improved network coverage.

To address this need, Milestone Communications is proposing the construction of a new wireless telecommunications facility at Collyar Park, located at 150 Collyar Park Circle, Laurens, SC 29360.

The proposed facility will feature a 230-foot self-supporting tower, along with the necessary ground equipment required for its operation. All equipment will be securely housed within a fenced enclosure at the base of the tower.

Both T-Mobile and AT&T plan to relocate their existing infrastructure from the water tank on West Main Street to this new, purpose-built tower to better serve the area with enhanced reliability and coverage.

Update #1: Upcoming community events:

Online Town Hall: On Tuesday, May 6th @ 6:00 pm we will hold an online Town Hall webinar consisting of a short presentation followed by a question and answer time. Registration is required and can be completed on the Town Hall page.

Our Process

1. Due Diligence 

Survey, FAA, FCC, NEPA, Phase 1, Geotechnical Analysis.

2. Land Use

Special Use Permit Application, Community Meeting, Staff Review, Planning Commission, Board of Supervisors.

3. Permitting

Conduct Bid Walk With Contractors and school/park representatives, submit Site Plan and Building permit applications.

4. Construction 

Tower construction = 4-6 weeks  | Carrier construction = 4-6 weeks on average

On-site supervision by Construction Manager | Schedule with schools/parks to minimize disturbance to student/park activities.

 

5. Site Maintenance

Four visits per year for site maintenance | Remove trash, debris, check signage. 

Annual RF testing | 2-4 visits per year for carrier modifications. 

About Us

With over 20 years experience, Milestone Towers is the leading developer of wireless infrastructure and cell towers in partnership with school, government and utility landowners.